EXTERIOR RENOVATIONS – HIGH LEVEL UPDATE

Dear Residents and Tenants:

We will strive to provide monthly updates on the status of the exterior renovations. This is a high-level update pulled from a site status report provided by RDH Building Science. Please note that we will continue to provide specific notices to units when we need access.

Phase 1 (Units “05”, “06”, “07” and “08”)

Scaffold Removal:Complete with some exceptions.
Miscellaneous:Remaining stucco and sealant work on base of building is underway. Need to remove beams to complete.
Miscellaneous:Once scaffolding removal is complete for both Phases, please report any additional “nail pops” or cracks so they can be addressed at end of project.

Phase 2 (Units “01”, “02”, “03” and “04”)

Window Deficiencies:Complete.
Scaffold Removal: Scaffold removal is underway and down to Level 14. They have added a second hoist to help with scaffold removal.
Miscellaneous:Lower floor finishing work is affected by beams which need to be removed to complete.
Miscellaneous: Once scaffolding removal is complete for both Phases, please report any additional “nail pops” or cracks so they can be addressed at end of project.
General Completion: Aiming for early June 2022.


If you have any questions, please do not hesitate to contact Cam Carruthers by email to: cam.carruthers@fsresidential.com.

Published by

Your PP2 Residential Committee

PP2 President until June 2, 2022.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s