Dear residents:
We strive to provide monthly updates on the status of exterior renovations.
This is a high-level update pulled from a site status report provided by RDH Building Science. Please note that we will continue to provide specific notices to units when access is required.
Phase 1 (Units “05”, “06”, “07” and “08”)
Window Deficiencies: Complete.
Scaffold Removal: Complete with some exceptions.
Miscellaneous: Remaining stucco and sealant work on base of building. Once scaffolding removal is complete for both phases, please report any additional “nail pops” or cracks so they can be addressed at end of project.
Phase 2 (Units “01”, “02”, “03” and “04”)
Window Deficiencies: On-going for interior deficiencies. Exterior deficiencies complete.
Scaffold Removal: Scaffold removal is underway and down to Level 22 but will be slow due to height and only one hoist now available.
Miscellaneous: Remaining stucco and sealant work on base of building. Beams supporting the scaffolding need to be removed before this work can be completed. Once scaffolding removal is complete for both phases, please report any additional “nail pops” or cracks so they can be addressed at end of project.
General Completion: Aiming for May 2022.
If you have any questions, please do not hesitate to contact Cam Carruthers by email to cam.carruthers@fsresidential.com.
Thank you for your cooperation.
Scaffolding is not complete as you suggest. We’re in Cave n. 508 and depressed waiting for removal. Please urge to hurry.
Barney Lukas
LikeLike
Sorry to hear of your depression, Barney. The delay at the lower floors of Phase I has been caused by ongoing work at the pool level. RDH assures us that the scaffolding will be removed as soon as possible. We’re getting close! Hang in there. If it’s any consolation, most of Phase II is still under cover as well.
LikeLike
Further to your query regarding the scaffolding on the 5th floor, RDH has just advised that it could be another six weeks until it comes down. Sorry.