EXTERIOR RENOVATIONS – HIGH LEVEL UPDATE

Dear residents and tenants,

We will strive to provide monthly updates on the status of the exterior renovations. This is a high-level update pulled from a site status report provided by RDH Building Science. Please note that specific notices will be provided to units when RDH needs access.

Phase 1 (Units “05”, “06”, “07” and “08”)
Final Colour Coat: 99% Complete. Need to complete roof, PH and scaffold areas.
Sealant: 95% Complete. Need to complete roof, PH and scaffold areas.
Window Deficiencies: On-going for interior deficiencies. Exterior deficiencies complete.
Miscellaneous: Remaining work on PH and base of building. Lower floor finishing work is affected by beams and require removal to complete.
Scaffold Removal: Down to Level 3.

Phase 2 (Units “01”, “02”, “03” and “04”)
Window Install: Complete except for Unit 301 and Swimming Pool Area. Level 3 – 95% Complete.
Roofing: Complete.
Stucco Framing: Complete
Stucco Scratch Coat: Complete up to Level 28
Stucco Colour Coat: Stucco scratch coat complete on elevator core.
Miscellaneous: River rock complete on elevator core roof. Metal roofs are being installed on PH – 95% complete. Lower floor finishing work is affected by beams and require removal to complete.

General completion: Aiming for April 2022.

If you have any questions, please do not hesitate to contact Cam Carruthers by email: cam.carruthers@fsresidential.com.

Your anticipated cooperation is appreciated.

Published by

Your PP2 Residential Committee

PP2 President until June 2, 2022.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s