EXTERIOR RENOVATION Update – Oct. 12, 2021

We will strive to provide updates every second week on the status of the exterior renovations. This is a high-level update pulled from a site status report of October 7, 2021. Please note that we will continue to provide specific notices to units when we need access.

Phase 1 (Units “05”, “06”, “07” and “08”)

  • Final Colour Coat: 99% Complete. Need to complete around roof and penthouse.
  • Sealant: 95% Complete.
  • Window Deficiencies: On-going for Interior deficiencies. Exterior deficiencies complete.
  • Scaffold Removal: Starting week of October 18, 2021 at Level 22 and above.

Phase 2 (Units “01”, “02”, “03” and “04”)

  • Steel Studs: Repairs at Roof are Complete
  • Sheathing: Complete
  • Wall Membrane: 95% Complete
  • Window Install: Level 27. Window installation complete by end of October.
  • Roofing: Level 3 – 95% Complete.
  • Stucco Framing: Level 21
  • Stucco Scratch Coat: Level 17
  • Thru Wall Flashing: Level 23
  • Drywall finishing is currently running five to seven weeks behind window installation and
  • is expected to speed up over time.

REMINDER: Blinds must be taken down before the window installation and, due to window warranty, not reinstalled by anyone other than a strata approved installer.

If you have any questions, please do not hesitate to contact Cam Carruthers at 604-648- 4443 or by email to: cam.carruthers@fsresidential.com.

Your anticipated cooperation is appreciated.

Published by

Your PP2 Residential Committee

PP2 President until June 2, 2022.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s