Dear residents and tenants:
We will be providing updates every second week on the status of the exterior renovations.
This is a high-level update and pulled from a site status report of June 17, 2021. Please note that we will continue to provide specific notices to units when workers need access.
Phase 1 (Units “05”, “06”, “07” and “08”)
Roofing: Level 22 92% Complete
Window Install: Complete
Cross Cavity Flashing: Complete
Stucco: Framing at Level 24, Mud at Level 20
EIFS: Level 21
Phase 2 (Units “01”, “02”, “03” and “04”)
Steel Studs: Level 8 – Structural Upgrades Ongoing
Sheathing: Level 6
Wall Membrane: Level 5
Window Install: Currently Underway on Levels 2 and 3
Roofing: Level 3 – 95% Complete, Level 22 – 95% Complete
EIFS Membrane: Level 2 and Level 3
Drywall finishing is currently running four to five weeks behind window installation and is expected to speed up over time.
REMINDER: Blinds must be taken down before the window installation and, due to window warranty, not reinstalled by anyone other than a strata approved installer. If you have any questions, please do not hesitate to contact Cam Carruthers at 604-648 -4443 or by email to: cam.carruthers@fsresidential.com.
Your anticipated cooperation is appreciated.