EXTERIOR RENOVATIONS – HIGH LEVEL UPDATE

Dear Residents and Tenants:

A high-level update will be provided every second week on the status of the exterior renovations. This update was pulled from a site status report dated February 25, 2021. Please note that specific notices will be provided to units when access is required.

Phase 1 (Units “05”, “06”, “07” and “08”)
Demolition: 98% Complete
Roofing: Level 3 and Level 22
Steel Studs: Complete up to Level 13
Sheathing: Complete up to Level 10
Peel & Stick: Complete up to Level 7
Window Install: Currently Level 9

Phase 2 (Units “01”, “02”, “03” and “04”)
Scaffolding: To be Completed Week of March 8, 2021
Demolition: Complete at Homer and Drake (Level 2 and 3). Remainder of demolition to start week of March 15, 2021.

Drywall finishing is currently running five to six weeks behind window installation and is expected to speed up over time.

REMINDER – Blinds must be taken down before the window installation and, due to window warranty, not reinstalled by anyone other than a strata approved installer.

If you have any questions, please do not hesitate to contact Cam Carruthers at 604-648-4443 or by email to cam.carruthers@fsresidential.com.

Your anticipated cooperation is appreciated.

Published by

Your PP2 Residential Committee

PP2 President until June 2, 2022.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s